Back to portfolio
Battery storage Chile construction

Atacama Storage

A 200 MW / 800 MWh battery co-located with Sierra Alta Solar, shifting midday generation to evening peaks.

Atacama Storage is a 200 MW / 800 MWh lithium-ion battery co-located with Sierra Alta Solar. The asset will charge from surplus midday solar generation and discharge during the evening peak, when spot prices are highest. Commissioning is expected in Q4 2026.

Nameplate capacity
200 MW
Commissioned
2026
Annual generation
—
CO₂e avoided
180 kt / year
Offtaker
Co-located with Sierra Alta Solar
200 MW / 800 MWhsolar-shiftingco-located

Project lifecycle

  1. Development

    Site selection, permitting, offtake structuring

    complete
  2. Construction

    EPC, equipment, energization

    current
  3. Operations

    O&M, performance monitoring, offtake delivery

    upcoming